Process automation

Reta Engenharia · ALICE Technologies

Vendor-reportedConstruction & real estateBrazilIn productionEnterpriseOther

Vendor-reported. The customer is named and the numbers are quoted from the source page, but the account comes from the vendor. No independent confirmation.

Reported by blog.alicetechnologies.com (vendor self-report). Checked against the source page on 2026-09-06. 5 of 5 figures below appear on that page word for word.

The problem

Traditional scheduling tools could not efficiently test multiple construction scenarios at scale or account for complex interdependencies, making it difficult to optimize the master plan while adhering to labor constraints and critical milestones.

What was deployed

Vendor
ALICE Technologies
Products
ALICE
Technique
Other
Build or buy
Bought off the shelf
Deployment
SaaS
Data used
project schedule/logic data, labor and equipment resource constraints, site accommodation capacity limits
Scale
One of Brazil's largest nickel/cobalt mining complexes: ~13 million m3 of earthworks, 110,000 m3 of reinforced concrete, 23,000 tons of electromechanical erection, direct labor capped at 3,200 workers.

What changed

Each row is quoted from the source. Figures we could not find on the page in those words are marked — they are kept, not deleted, so you can judge them.

labor idle time

10% less labor idle time

Quoted word for word from the source · round percentage, no baseline given

equipment idle time

33% less equipment idle time

Quoted word for word from the source

peak resource utilization

24% lower peak resource utilization

Quoted word for word from the source

time to analyze and generate scenarios

The team analyzed and generated scenarios 50% faster

Quoted word for word from the source · round percentage, no baseline given

time spent on resource leveling

reduced time spent on resource leveling by 44%

Quoted word for word from the source

No impactimpact on commissioning or production milestones

No impact on commissioning or production milestones

Quoted word for word from the source

At Reta Engenharia, innovation is more than a value. It is part of our DNA. High-complexity projects require not only experience but new ways of thinking and acting. Partnering with ALICE allowed us to combine both, bringing agility and intelligence to how we plan and execute large-scale projects.
Fernando Ferri, Project Manager, Reta Engenharia

Difficulties and limits

Sources

Similar deployments

Shriram Finance

less than 3–4 hours — Onboarding Turn-Around-Time (TAT)

Independently reportedBanking & finance · Process automation · Classical ML · In production

GE Aerospace

Independently reportedManufacturing · Process automation · Classical ML · Scaled

Apollo Tyres

under 10 minutes — Time for root cause analysis

Independently reportedManufacturing · Process automation · AI agents · In production

Broadcom · Moveworks

88% — autonomous IT resolution rate

Independently reportedTechnology & software · Process automation · NLP · Scaled

icare · SAS

increased by 15% — accuracy

Independently reportedInsurance · Process automation · Classical ML · Scaled · 2019

Amazon · Amazon

10% more — shopper spend

Independently reportedRetail & e-commerce · Process automation · Computer vision · Scaled · 2024